The timeline below is for both the 170th Avenue and Florence Street projects, and is subject to change.

 
  • Preliminary design (current status)

    Through December 2020
  • Right-of-way acquisition

    March-November 2021
  • Final design

    May 1, 2021
  • Contractor bid process

    January-February 2022
  • Start of construction

    March 2022
  • Project completion

    August 2022